K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
F

Failure to Maintain Required Annual Generator Maintenance Documentation

Christian Care Nursing CenterMuskegon, Michigan Survey Completed on 03-26-2025

Summary

The facility failed to maintain its emergency generator system in accordance with NFPA 110, NFPA 99, NFPA 111, and NFPA 70 standards. During a record review conducted on March 26, 2025, it was found that the facility did not provide the required annual generator preventative maintenance report. The last available report was dated 3/20/24, indicating that the annual maintenance had not been documented for the current year. This deficiency was confirmed through an interview with the facility Maintenance Director at the time of the record review. The absence of the current annual preventative maintenance report means the facility could not demonstrate compliance with required generator maintenance protocols, which are essential for ensuring the emergency power system's reliability in the event of a main utility power loss.

Plan Of Correction

K918 1. No residents were harmed as a result of this deficient practice. 2. The annual generator preventative maintenance and testing has been completed on 4/3/2025. 3. The QAPI Committee has directed the Director of Plant Operations/designee to perform weekly generator load tests as scheduled and submit the results of those tests to QAPI. The Administrator is responsible for ensuring that substantial compliance is attained through the Plan of Correction and is maintained thereafter. The results will be provided to the QAPI Committee for further follow-up and review.

Penalty

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
See other K0918 citations
Failure to Perform and Document Annual Main and Feeder Breaker Testing
F
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors found that the facility failed to perform and/or document required annual testing and exercising of main and feeder circuit breakers in accordance with NFPA 99 and manufacturer recommendations. During record review, no documentation could be produced to show that the annual breaker exercises had been completed, and the Director of Facilities acknowledged this lack of records. This deficiency relates to the essential electrical system that supports life safety and critical branches during emergencies.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Exercise and Document Main and Feeder Breaker Maintenance per NFPA 99
F
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors found that the facility did not have documentation showing that the essential electrical system’s main and feeder circuit breakers were exercised annually in accordance with manufacturer recommendations and NFPA 99 requirements. During record review with the Maintenance Director, no records could be produced to verify that these breakers had been properly exercised, and the Maintenance Director acknowledged this failure. This deficiency was cited as affecting all occupants due to noncompliance with required essential electrical system maintenance and testing standards.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Perform and Document Required Generator Battery Testing
F
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors found that the facility failed to perform and document required testing of backup generator batteries in accordance with NFPA 110. During record review, no documentation of generator battery testing was available, and the Maintenance Director acknowledged both the lack of records and a lack of knowledge of the NFPA 110 battery testing requirements. The report notes that this failure could result in loss of power affecting life support and life safety features for occupants.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Maintain Required Generator Battery Testing Documentation
D
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors identified a deficiency when the facility could not provide documentation that backup generator batteries were being tested in accordance with NFPA 110 and NFPA 99 requirements. During record review, no records of generator battery testing were available, and the Maintenance Director confirmed he was unable to locate the requested documentation. This failure concerns the essential electrical system that supports life safety and critical functions during power loss.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Perform Required Generator Battery Conductance Testing for Essential Electrical System
F
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors found that the facility failed to maintain its Essential Electrical System (EES) in accordance with NFPA 99 and related standards when record review showed that conductance testing was not performed for 2 of 2 sealed generator batteries over a defined period, and only one generator battery was tested during that time. During an interview, the Maintenance Director acknowledged that required testing had not been completed for both batteries. This lapse in required emergency power system maintenance affected the facility’s single EES and all residents and staff relying on it.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.
Failure to Maintain and Document Required Generator Testing and Safety Features
F
K0918 K918: Have generator or other power source capable of supplying service within 10 seconds.
Short Summary

Surveyors found that the facility failed to maintain required documentation showing that its three generators were tested monthly and inspected and tested annually in accordance with NFPA 99 and NFPA 110. Despite multiple requests, no records of these tests or inspections were provided. During the facility tour, surveyors also observed that none of the three generators were equipped with remote manual stop buttons, and this was confirmed by the Maintenance Director. This deficient practice had the potential to affect all residents in the facility.

No penalty information released
tooltip icon
The penalty, as released by CMS, applies to the entire inspection this citation is part of, covering all citations and f-tags issued, not just this specific f-tag. For the complete original report, please refer to the 'Details' section.

Know what gets cited — and walk into your next survey with full visibility

We process and analyze inspection reports and Plans of Correction using AI to surface insights and trends — so you can improve care quality and stay ahead of compliance risk before your next survey.

Get ready for your next survey

See what surveyors are citing in your state and spot your risk areas before they do.

Monthly Citation Reports

Have you been cited for this tag?

Save hours drafting a compliant Plan of Correction — AI built on real approved POCs.

Plan of Correction Writer

Trusted data from CMS and state health departments

Every citation, penalty and Plan of Correction is sourced from public CMS records (latest release June 24, 2026) and official state health department websites — never guesswork.

Trusted by long-term care providers and associations.

Allegria Senior Living logo
FHCA logo
WeCare Centers logo
Care Rehab logo
An unhandled error has occurred. Reload 🗙